Not for several more years. The Georgia Department of Transportation is widening State Route 20 to six lanes in six sections between I-575 in Canton and North Corners Parkway in Cumming, and while the two sections closest to Canton were more than 94% complete in November 2026, the last section to start, from Union Hill Road to East Cherokee Drive, was awarded in September 2026 with completion expected in 2031. The overhead sign on I-575 in Canton in the photo above was already pointing drivers to "East 20, Cumming" in 2004, and the road between the two has been under construction in one section or another since 2020.
This post is for homeowners, buyers and commuters along the corridor in Cherokee and Forsyth counties who want plain answers: where each section stands, what the finished road will look like, how left turns will work, and what the project means if you live on or near it. Every status figure below comes from GDOT's own project dashboard, checked on November 18, 2026. Percent-complete numbers change monthly, so treat them as a snapshot.
It is a series of six GDOT projects that together widen SR 20 from just east of I-575 in Canton to east of North Corners Parkway in Forsyth County. GDOT describes it as one larger project built in phases. The first phase started construction in 2020, and the contract for the sixth and final phase was awarded in September 2026.
The finished road is the same design along the whole corridor: six lanes, three in each direction, separated by a 20-foot raised median. GDOT's project descriptions add curb and gutter in the more urban sections, upgraded pedestrian and bicycle access in the Cherokee sections east of Union Hill Road, and a 5-foot sidewalk on both sides in the Forsyth section between Post Road and North Corners Parkway.
GDOT's stated goals are less congestion, better safety and room for growth. Its descriptions of the two eastern Cherokee sections say the work aims to "reduce traffic congestion, enhance safety, and better accommodate future growth in the area." In the September 2026 announcement, GDOT District Six Engineer Grant Waldrop put it this way: "Widening State Route 20 improves traffic flow and allows for the continued growth along this important roadway."
For drivers, the practical changes are more lanes for through traffic and fewer places where a car has to cross several lanes of oncoming traffic to turn left, which is where the median and the U-turns come in.
Here is each section from west to east, with the status shown on GDOT's GeoPI project dashboard on November 18, 2026.
Section (west to east) | GDOT project | County | Status | Construction complete |
|---|---|---|---|---|
East of I-575 in Canton to east of Scott Road | 0009164 | Cherokee | Under construction | 94.56% |
Scott Road to Union Hill Road (about 2 miles) | 0014131 | Cherokee | Under construction | 98.59% |
Union Hill Road to East Cherokee Drive | 0014132 | Cherokee | Under construction | 0.00% |
East Cherokee Drive to SR 369 (about 2.1 miles) | 0014133 | Cherokee | Under construction | 8.60% |
SR 369 to Post Road (about 6.3 miles) | 0002862 | Cherokee and Forsyth | Under construction | 20.78% |
Post Road to east of North Corners Parkway | 0003682 | Forsyth | Under construction | 32.12% |
The pattern is easy to read. The Canton end is nearly finished. The middle of the corridor, from Union Hill Road east to SR 369, is where most of the remaining work sits, and the long stretch across the county line into Forsyth is roughly a fifth of the way done.
GDOT expects the final section, Union Hill Road to East Cherokee Drive, to be completed in 2031. In its September 25, 2026 announcement, GDOT said C.W. Matthews Contracting Co. won the $61.1 million contract, that the section spans about 4.2 miles, and that work would likely get underway within about two months. GDOT's dashboard lists the section at about 3.9 miles, so expect to see both figures quoted.
GDOT's dashboard does not currently post completion dates for every section, so 2031 is the most reliable date for when the whole corridor will be six lanes. Construction schedules can move with weather, utilities and right-of-way work, and we would rather give you the agency's date than guess at a better one.
Three lanes in each direction with a raised median down the middle. That median changes how the road works more than the extra lanes do. On most of the corridor, GDOT says access to side roads and driveways will be controlled by Restricted Crossing U-Turns, usually called RCUTs, placed in the median. GDOT also notes that RCUT locations shown in early layouts can change during design, and that truck turnarounds are included at some RCUTs near businesses that draw tractor-trailers, such as farms, landscaping suppliers and stone yards.
In the Forsyth section, GDOT adds turn lanes at major driveways and intersections, plus sidewalks on both sides of the road. In the Cherokee sections east of Union Hill Road, GDOT's descriptions include upgraded pedestrian and bicycle access.
If you have not driven one yet, here is the short version from GDOT's own RCUT brochure. Traffic on Highway 20 can still turn left, turn right or go straight as usual. Traffic coming from a side street or driveway can only turn right onto the highway. To go left, you turn right, drive a short distance to a designated U-turn opening in the median, and come back. To cross the highway to the street on the other side, you turn right, make the U-turn, and then turn right onto that side street.
It feels roundabout the first few times. GDOT's case for it is safety: the brochure says nearly one-third of fatal crashes in Georgia are intersection related, many of them angle collisions involving a driver crossing or turning left from a side street. GDOT reports that, nationally, RCUTs have cut fatal crashes by 70% and injury crashes by 42% where they were installed, and reduce conflict points by about half compared with a conventional intersection. Some RCUTs and U-turns also have traffic signals, which GDOT calls a superstreet.
It depends on how close you are to the road.
It is also worth being plain about what the project does not do. Widening the road does not move county lines, city limits or school attendance zones. Those follow your parcel, not the pavement. If you are on the Forsyth end, our Cumming area page covers parks and daily life there.
A few minutes of homework saves surprises later:
None of this is a reason to avoid the corridor. It is simply part of knowing the house you are buying, the same way you would check a flood map or an HOA's rules. Our Canton area guide covers the rest of daily life in Canton.
Buyers will ask about the road, so have the answers ready. Know which section your home is on, its current status, and how your entrance will work when the median is built. A seller who can pull up the GDOT project page and explain the turn pattern in two sentences tends to come across as prepared, and buyers notice.
It also helps to describe the finished road accurately. "Six lanes with a raised median" is a fact. Claims about what the road will do for home values are not, and nobody can promise them, so we leave them out.
GDOT's advice for this corridor is to expect delays, slow down in work zones and check conditions before heading out. Real-time information is available by calling 511, at 511ga.org or through the Georgia 511 app. Some of the work happens overnight. In April 2026, for example, Forsyth County News reported GDOT beginning nightly lane shifts on the Forsyth County stretch.
If you are weighing a home on the corridor and a job in another direction, test the drive during the week before you commit.
GDOT expects the final section, Union Hill Road to East Cherokee Drive, to be finished in 2031. The contract was awarded in September 2026, and the two sections nearest Canton were more than 94% complete in November 2026.
Six, three in each direction, separated by a 20-foot raised median, from just east of I-575 in Canton to east of North Corners Parkway in Forsyth County.
A Restricted Crossing U-Turn. Drivers on the highway can still turn left, turn right or go straight. Drivers from side streets turn right, then use a U-turn opening in the median to go left or cross the highway.
GDOT's dashboard lists C.W. Matthews Contracting Co. on five of the six sections and Vertical Earth Inc. on the Scott Road to Union Hill Road section.
GDOT awarded the Union Hill Road to East Cherokee Drive section for $61.1 million in September 2026.
GDOT's GeoPI project dashboard shows status and percent complete for each section by project number. For live traffic and lane closures, call 511 or visit 511ga.org.
Thinking about what your home near the corridor is worth today? Start with a home valuation.
Start Your New Home Search Now!
Stay up to date on the latest real estate trends.
You’ve got questions, and we can’t wait to answer them.